Back to Projects
In Execution #102-INFRA

Mai Mahiu Primary School Roofing

Mai Mahiu, Nakuru Est. Completion: May 2026

Project Description

This project involves the complete re-roofing of 6 classrooms at Mai Mahiu Primary School. The original structures were damaged during the heavy rains in November 2025. Following a formal request submitted by the school committee and assessed by the KenGen Liaison team, the project was approved for execution under the CSR education infrastructure fund.

The scope includes removing the old asbestos roofing, structural reinforcement of the timber trusses, and the installation of new prepainted corrugated iron sheets. Rainwater harvesting gutters will also be installed to supply the school's water tanks.

Execution Progress

Overall Completion 65%
Contractor
Rift Valley Builders Ltd
Budget Allocation
Ksh 1,200,000

Community Impact

  • Safe learning environment for over 300 pupils.
  • Improved rainwater harvesting capacity (10,000 Liters).
  • Local employment during the construction phase (15 youths).

Request Workflow

1. Log & Acknowledge

Request received via Online Portal and acknowledged.

Jan 12, 2026

2. Screen & Review

Initial screening by Liaison Office completed.

Jan 15, 2026

3. Assess & Consult

Field visit conducted by KenGen engineers to assess damage.

Feb 02, 2026

4. Feedback & Reporting

Budget analyzed and Management approval obtained.

Feb 20, 2026

5. Execute Project

Responsibility assigned to contractor. Work in progress.

Started: Mar 05, 2026